This is a an update of the last fortnight because it’s all text and no pictures so I thought merging would be a good idea! I’m sorry it’s rather devoid of pictures but it’s nearly impossible to see what’s changed, so there wasn’t much point in taking photos!

So, 30th – 4th they built the walls up higher (they couldn’t reach before they had the scaffolding).

They’ve also done some demolishing of our front garden and drive because we’re having a bigger drive (I hate the idea but not my decision :lol:)

We were expecting the roof timbers at the end of that week but the suppliers let us down AGAIN and they didn’t arrive. They’re meant to be here on the 18th now but he’s going to have words so hopefully they’ll be here earlier. Because they’re not here and were meant to be they’ve now run out of things to do on the actual building.

So 7th – 11th was spent doing more work on our front drive, starting to put slabs down at the back which are going to replace our concrete path and also started building the brick wall which is going to be down the side of the ramp.

Good news is that the roof timbers are meant to arrive on Tuesday 15th which is better than the Friday!